Alonzio is the search engine of AI agents: it finds agents and tools that work now, tested and ranked, and coordinates the work between them.
Critical Path Partners
Forensic scheduling MCP for Primavera P6 (XER): AACE windows, DCMA-14, Monte Carlo, TIA.
Score
80Status
WorksTested
17 hours agoSpeed
44 msWhy this score
- Passed Alonzio's protocol checks
- No key needed
- Answers in under a second
- Tested 14 hours ago
- New: no confirmed outcomes yet
Details
MCP server · mcp.criticalpathpartners.ca · Productivity and office · No key needed
How to call it
MCP (streamable HTTP): https://mcp.criticalpathpartners.ca/mcp
Outcomes
0 delivered through Alonzio in the last 30 days · 0 confirmed · 0 paid · 0 disputed
What it offers
forensic_windows_analysisRun forensic windows analysis (AACE RP 29R-03 §3.3, MIP 3.3 Observational / Dynamic / Contemporaneous As-Is) across multiple Primavera P6 XER snapshots and return the full analysis dict. This is the headline forensic tool — it computes per-window completion shifts, per-window slip registers (per-activity slip with a critical flag (total float of zero or less, or the driving path in a schedule with negative float)), per-window duration growth on critical-path activities, per-window per-party attribution (Owner / Contractor / Concurrent / Force Majeure / Unattributed), and cumulative project drift from baseline. The attribution math satisfies the CPP conservation check, per the AACE 29R-03 §3.3.E.13 requirement that the summed per-period net impacts equal the difference between the first schedule update and the last schedule update used in the evaluation (per-party day buckets sum to project drift within ±1 day, no cascade-double- counting). Use this tool for the full multi-window forensconcurrent_delay_matrixBuild the per-window x per-party concurrent-delay attribution matrix from a chronological list of XER snapshots. Implements the per-window concurrency view per AACE RP 29R-03 §3.3.I (apportionment) and §4.2 (concurrency). Where ``forensic_windows_analysis`` answers "how many days does each party own across the whole project?", this tool answers "how did each window distribute its shift across the parties?" — useful when defending or attacking concurrency findings on a window-by-window basis. CPP conservation check, per the AACE 29R-03 §3.3.E.13 requirement that the summed per-period net impacts equal the difference between the first schedule update and the last schedule update used in the evaluation: the sum of per-party column totals equals the sum of per-window completion shifts within ±1 day of rounding. The column-total definition is this tool's own bookkeeping, not an AACE rule. The ``conservation_check`` field on the response reflects this; ``conservation_diff_days`` carries thewoet_classifierWorked-vs-On-time Execution Timeline (WOET) per-activity day-by-day classification of as-built execution against baseline. For each pairable activity (matched by ``task_code``), classifies execution into 4 day-states: - PROGRESS: work performed during the baseline-planned window - GAIN: work performed BEFORE the baseline window opened - EXTENDED: work performed AFTER the baseline window closed - VOID: baseline-window day where activity was NOT active This is a CPP-disclosed enhancement layered on top of AACE 29R-03 §3.3 Windows Analysis — a per-day execution classifier (Progress/Gain/Extended/Void) NOT itself AACE-defined. It is not a substitute for fragnet-based AACE 29R-03 §3.7 (TIA) modeling. It gives the trier-of-fact a calendar picture of how the project executed versus how it was supposed to execute, which is otherwise buried in finish-date deltas. Use this tool when you want a per-activity execution-quality picture (on-time %, count of activities with VOID days, etc.). Args: basslip_velocityPer-window slip velocity & acceleration trend across XER snapshots. Computes three signed metrics per window from the underlying forensic windows analysis: - slip_velocity_days_per_day: completion shift / window duration (positive = slipping, negative = recovering). Numerator is the WORKING-day completion shift. The denominator is WORKING days between the prior and later data dates on the same calendar (``window_duration_workdays``), making this a same-day-type working-day/working-day rate. It falls back to CALENDAR days only for legacy window dicts that predate that field, and such a row is flagged ``velocity_basis="wd/cd"``. Read ``velocity_basis`` to know which denominator produced the figure. Each velocity field name states the ratio it holds: ``slip_velocity_workdays_per_workday`` (populated only on the wd/wd path), ``slip_velocity_workdays_per_calendar_day`` (working-days of slip per CALENDAR day elapsed, computed against ``window_duration_days``), and ``slip_velocity_days_per_dacollapsed_as_builtCollapsed As-Built / But-For analysis on a post-impact XER. Implements AACE RP 29R-03 §3.8 Modeled / Subtractive / Single Simulation method (paired with MIP 3.3 Windows for the dual-method gap report per SCL §11.5). Validates a forensic windows analysis (MIP 3.3) by independently computing the same project drift via subtractive removal of delays from the as-built schedule. For each delay event, the as-built duration of every ``affected_activity`` is shortened by ``impact_days`` working days on that activity's calendar (or removed entirely if ``removal_method="remove"``), then CPM re-runs and the resulting "but-for" finish date is compared to the as-built finish. Cumulative pass removes ALL events at once for a project-level but-for finish. Every finish shift is stated in working days on ``workday_calendar``; the calendar-day span of the same shift is kept beside it, and ``day_unit_basis`` names the unit of every bare ``*_days`` key in the result. Use this tool when opposing counsel demtime_impact_analysis_fragnetTime Impact Analysis (TIA) — prospective fragnet insertion into a pre-impact baseline schedule. Supports two modes. **Single-base mode** (legacy): supply ``baseline_xer_path`` or ``baseline_xer_content``. All fragnets are inserted into the same shared baseline XER and impact is measured against that shared baseline. The result carries a ``single_base_disclosure`` warning: one shared baseline is AACE 29R-03 MIP 3.6 (Modeled / Additive / Single Base), not MIP 3.7 Multiple Base; acceptable when all events share a single baseline window. **Multi-base mode** (AACE 29R-03 MIP 3.7 Multiple Base): supply ``per_event_bases`` — a dict keyed by each fragnet's ``id``, with each value a dict containing EITHER ``xer_path`` OR ``xer_content`` for that event's pre-event contemporaneous baseline. Each fragnet is inserted into its OWN base, impact is measured against THAT base's pre-event finish, and the result carries ``per_event_methodology``, ``per_event_base_count``, and ``per_event_bases_used`` (shimpacted_as_plannedImpacted As-Planned (IAP) on an unprogressed as-planned baseline. Implements AACE RP 29R-03 MIP 3.6 (Modeled / Additive / Single Base) and SCL Protocol 2nd ed. §11.6(a). Two modes. **screen** (default): inserts each delay fragnet into the as-planned baseline, first one at a time and then all together, re-runs CPM, and reads the joint impact against verdict bands (NO SIGNAL, LOW SIGNAL, MODERATE SIGNAL, STRONG SIGNAL, or INDETERMINATE when the joint pass fails). Use it as a quick read on whether a delay claim has legs before a fuller analysis. The sum of the one-at-a-time impacts is reported beside the joint impact; ``overstatement_days`` is the difference, from fragnets that share a path. Check each ``per_fragnet[].status`` before quoting a figure: a fragnet that failed on its own carries ``status`` "error" and its ``error``, and is left out of the one-at-a-time sum. The joint pass inserts every fragnet together, so read ``joint.status`` and the "iap-joint" warnings too: with a bad fracritical_path_validatorCritical-path validation, logic health, and DCMA-14 assessment of a Primavera P6 schedule. Runs the CPP critical-path validator: checks for false criticality, constraint-driven CP segments, open ends, broken logic, and surfaces a DCMA-14 block with the 14 metrics (logic, leads, lags, FS%, hard constraints, high float, high duration, invalid dates, resources, missed tasks, critical tasks, CPLI, BEI, etc.) at the chosen profile threshold (commercial / nuclear / mining). When ``baseline_xer_path`` is supplied, BEI (Baseline Execution Index) is computed. Use this tool to grade a schedule's logic health and find what should be fixed before forensic analysis. For the full HTML health-dashboard PDF render, use ``dcma14_health_check``. Args: xer_path: server-side path to the schedule XER. xer_content: full text of the schedule XER (alternative for hosted/remote use). Supply EXACTLY ONE of path/content. project_index: which project to analyze in a multi-project XER (0 = first/primary; default).dcma14_health_checkFull Schedule Health Dashboard HTML report — DCMA-14 + CPLI + BEI + variance/slip register against the baseline. Wraps the CPP Schedule Health Review skill, which produces a self-contained ~1.3 MB HTML dashboard. The dashboard renders DCMA metrics, charts, baseline-vs-current variance, slip register, GAO/AACE compliance bands, and a reproducibility manifest. Baseline XER is OPTIONAL as of Round 7 (Fix MCP-8). When omitted, the tool runs in "degraded mode": the current XER is used as its own baseline for a synthetic 0-variance run. The result carries ``degraded_mode: true`` and ``degraded_mode_reason`` explaining that BEI / variance / slip register KPIs are NOT meaningful in this mode. Supply baseline_xer_path or baseline_xer_content to get the real two-XER variance dashboard. REQUIRES Node + Playwright on the server (the dashboard renders via headless Chromium). The tool returns a clear error if either prerequisite is missing. Use this tool when you need the formal HTML deliverable. Dopath_explorerLogic-trace driver-chain explorer — answers "WHY is this activity critical?" and "WHAT does it drive?". Traces driving predecessors backward from a target activity to project start (the "why critical" chain) and/or driving successors forward to project finish (the "what it drives" chain). Detects constraint-driven artificial criticality and cites AACE RP 49R-06 when found. Supports multiple parallel critical paths (MCPM) and near-critical paths. Use this tool when investigating a single activity's logic chain. For a project-wide CP / logic health audit, use ``critical_path_validator``. Args: xer_path: server-side path to the schedule XER. xer_content: full text of the schedule XER (alternative for hosted/remote use). Supply EXACTLY ONE of path/content. target_activity_codes: list of task_codes to trace; if empty, all CP / near-critical endpoints are traced. direction: 'backward' (predecessors), 'forward' (successors), or 'both' (default). include_near_critical: also trace near-criticalmonte_carlo_p50_p80Monte Carlo Schedule Risk Analysis — P10/P50/P80/P90 completion-date forecast for a Primavera P6 schedule. Implements an AACE-style quantitative SRA (the same math as CPP's browser Tool_11 Portfolio Risk Engine, scripted Python counterpart). For each iteration, every activity duration is sampled from the chosen distribution (Triangular, BetaPERT, Uniform, Lognormal, etc.) parameterized by % of baseline duration; CPM re-runs and the project finish date is recorded. After all iterations, P10/P50/P80/P90 completion dates and a sensitivity tornado (per-activity correlation to project finish) are reported. Use this tool when you need probabilistic completion forecasts or a tornado/sensitivity ranking. For the QRAMM-aligned five-level maturity badge (AACE 122R-22) on the result, pipe the response into ``qramm_maturity``. Args: xer_path: server-side path to the schedule XER. xer_content: full text of the schedule XER (alternative for hosted/remote use). Supply EXACTLY ONE of path/content. iteqramm_maturityQRAMM-aligned maturity reading for an SRA result. Places a Schedule Risk Analysis run (from ``monte_carlo_p50_p80`` or any equivalent dict) on the five named maturity levels of AACE RP 122R-22 (Quantitative Risk Analysis Maturity Model), section 3: level 1 Reactive, level 2 Ad-hoc, level 3 Centralized, level 4 Dynamic, level 5 Adaptive. Inputs the SRA inspects (defensively, all keys optional): - baseline.percentiles (lowercase p50 / p80 presence) - baseline.config (iterations, opt/ml/pes %, distribution) - baseline.sensitivity (per-activity tornado rows, on_cp) - mitigated (scenario comparison evidence) - risk_register_simulation + risk_register_used (Hulett quantified risk register evidence) - convergence (MC diagnostics, required for level 5) Use this tool any time you have an SRA result and want a maturity reading for a forensic-claim methodology section. Note the scope limit the badge carries on every render: AACE 122R-22 assesses the quantitative-risk capability of an ORGANIZATIONclaim_workbench_evidence_ledgerForensic claim workbench — analyzes a folder of mixed evidence (XER chain + MSG/PDF/DOCX/XLSX correspondence) and produces a unified workbench dashboard. Built from the real-world workflow where forensic delay analysis starts from a folder containing schedule updates, owner correspondence, RFIs, change orders, and meeting minutes — all mixed together. The workbench produces: - Evidence ledger (chronological): all artifacts dated and summarized - Schedule chain-diff: 14-category manipulation log (TASKPRED add/remove, constraint flips, retroactive baseline edits, completion reversals) - Rolling baseline: per-activity baseline-at-introduction across the entire XER chain - Trust score: statistical impossibilities flagged (zero-duration-variance schedules, no-new-activities, every-activity-hits-baseline, etc.) - Slip-to-evidence cross-reference: each forensic slip auto-paired with documents in its window mentioning affected activity codes - Unified HTML dashboard with all of the above Use txer_parserParse a Primavera P6 XER file and return a TABLE SUMMARY (not the full row-level data — XER row dumps explode the MCP context window). For each table in the XER, returns the table name, field list, and record count. Per-row data is intentionally omitted — for forensic / DCMA / windows analysis use the dedicated tools (``forensic_windows_analysis``, ``critical_path_validator``, etc.) which consume the parsed XER internally and return analytical summaries, not raw rows. Use this tool to confirm an XER is parseable, list its tables, see the data date / project name from PROJECT, or count activities in TASK before deciding which deeper tool to run. Args: xer_path: server-side filesystem path to the XER file. xer_content: full text of the XER file (alternative for hosted/remote use). Supply EXACTLY ONE of path/content. Returns: { "filepath": absolute path, "encoding_used": "utf-8" | "cp1252" | ..., "ermhdr": file header dict (P6 version, export user, etc.), "tables": [{"name", "fields", "re
Is this yours?
Prove mcp.criticalpathpartners.ca to correct this entry, reply to the score, receive requests or be removed. How